A New Upper School for Sidwell Friends
In June 2024, Sidwell Friends began work to renovate the Upton Street building, once the Washington Home & Community Hospices nursing home, into a new Upper School for grades 9-12. The school will open in the fall of 2026 and will be the largest building on campus, at more than 130,000 square feet.
The project marks the next stage of the School’s long-held dream of reuniting all three divisions—the Lower, Middle, and Upper Schools—on the Washington, DC campus for the first time in more than 60 years since the Lower School moved to Bethesda, Maryland. Once the Upper School is complete, Sidwell Friends will begin raising the necessary funds to renovate the current Upper School, located at the center of campus, into a new Lower School for grades preK-4.
- Construction Timeline and Updates
- Livestream Monitoring Video of Upton Street and 37th Street
- New Upper School at a Glance
- Project Goals
- Building Renderings
Construction Timeline and Updates
March 14, 2025
Work continues apace on the new Upper School as spring approaches. Inside the building, there’s a lot of new framing in place, and visitors are beginning to imagine some of the new spaces. Here are a few other updates:
- Pepco will begin work next week on installing new electric service conduits to the site. The new protective fence installed this week along 37th Street near Upton Street will keep this area safe while that work is going on. We expect this work to continue through much of April.
- The utility contractor has begun installing storm drainage pipes on the site; that work will continue through the summer.
- Crews are still pouring concrete foundations that will support new areas of construction. We expect structural steel to go up in areas of new construction beginning the week of March 24.
- Work on the building façade will begin in April and continue into the fall.
January 15, 2025
The favorable weather we experienced during the fall has given way to what we hope is a relatively brief winter cold spell. But work on our new Upper School proceeds apace. Here’s the latest:
- The job site will be closed on Monday, January 20.
- Work crews will be demolishing a portion of the retaining wall between the Upton building and the rest of the campus through the end of January. This is near where the now-demolished systems wing of the building used to stand.
- Also this month, electric service lines will be installed from the existing PEPCO switch on 37th Street through the site to the north wing of the building.
- Workers will begin installing micropile foundation supports for the new cafeteria and stairwell additions late next week. This work will continue through mid-February.
- When that is complete, contractors will pour the concrete foundations.
Looking further ahead:
- February - June: Installation of structural steel in the areas of new construction.
- April - September: Work on the building façade, including areas of new construction.
- May - December 2025: More utility installation.
December 5, 2024
Good news! Contractors will finish drilling the geothermal wells on Monday, December 9. Demolition of the HVAC systems wing of the building is progressing well and will wrap up on Friday, December 13. With that, two of the most impactful activities associated with the project will be complete.
Two other pieces of work will wrap up before the holidays:
- Demolition of a portion of the back (campus) side of the building
- Grading of the site and the removal of asphalt and some curb and gutter sections.
Both are scheduled to be complete by Friday, December 20.
The installation of micropiles on the south (campus) side of the property that will support the new cafeteria addition has been pushed to January.
The construction site will be closed on Christmas and New Year’s Day.
November 26, 2024
Here’s our latest progress video. Demolition of the large HVAC systems wing of the building on the south (campus) side of the site is underway. Well over half of the 120 geothermal wells are now complete, and drilling is on schedule to wrap up on or around December 9. Inside the building, workers are framing classrooms, labs, offices, and common spaces. Happy Thanksgiving to all!
November 15, 2024
Due to the acceleration of the geothermal well drilling from winter/spring of 2025 to the fall of 2024, the contractor has updated the schedule of work for the coming months. The schedule below replaces the one we posted on August 12.
- Now – Early December 2024: Continuation of the drilling of geothermal wells
- Now – Early December 2024: Complete demolition of the two-story central plant on the south (campus) and east (37th Street) side of the property. This structure houses the heating and air conditioning systems that will be replaced by the geothermal system.
- November – December 2024: Installation of micropiles on the south (campus) side of the property that will support the new cafeteria addition
- January – April 2025: Installation of structural steel in areas of new construction
- January – July 2025: Work on building façade, including areas of new construction
- July – November 2025: Installation of utilities on the project site.
The drilling for the micropiles will take place primarily on the south and east side of the campus and will generate much less noise than the drilling of the geothermal wells.
As of November 14, the contractor has completed drilling more than 50 of the 120 wells and that number is increasing by five each day. We are still on track to complete the drilling on or about December 9.
October 18, 2024
Washington Gas advised our contractor today that it will be closing Quebec Street in the vicinity of 37th Street next week (October 21-25) as part of the ongoing Washington Gas project. Construction vehicles needing access to Sidwell’s new Upper School project will use the detour route Washington Gas has provided.
October 15, 2024
One of the features of the new Upper School is a system of geothermal wells that will use the constant temperature of the earth below ground to heat and cool the building. The drilling of these wells is a major component of the project. In all, there will 120 wells around the building, averaging about 600 feet in depth.
Drilling these wells is loud work. The original construction timetable called for that work to take place over 18 weeks in the spring of 2025. But our contractor recently presented us with the opportunity to reduce the duration of the work to six weeks, thanks to the unexpected availability of three additional drilling rigs.
To take advantage of the opportunity, drilling work will begin on October 28 and, barring an unforeseen issue, will be completed by December 9. An added benefit of this project acceleration is that the drilling will coincide with the demolition of the east (37th Street) side of the building, which is set to begin on October 21 and end by Thanksgiving.
In all, this change will reduce the total duration of loud, project-related noise to six weeks from the original expectation of more than five months—one month for building demolition and four months for well drilling.
There will be no work, either drilling or demolition, on Thanksgiving or the Friday after.
We appreciate your understanding as we move through this process. The new Upper School, which has been designed to meet LEED Gold certification, will significantly reduce our school’s carbon usage. As an added long-term benefit, the geothermal system will eliminate the need for roof-top cooling towers and the constant noise they create.
October 11, 2024
An update to our September 27 post: demolition of the east (37th Street) side of the building is now scheduled to begin the week of October 21. That’s a delay of one week. The contractor expects to complete the work by Thanksgiving. This work will be loud at times, particularly around the end of the month and early November, when the concrete is broken up for removal.
In the meantime, tree removal and wood chipping around the building is scheduled to be complete by the end of October.
September 27, 2024
During the week of October 14, work will begin on a significant milestone in the Upton project: the demolition of a large portion of the east (37th Street) side of the building. This wing served as the main entrance for the former nursing home, contained several multi-purpose rooms that were used as Sidwell Friends classrooms in recent years, and housed the building’s heating and air conditioning systems. In all, the section being demolished represents about 18 percent of the building’s current footprint. The contractor estimates that the work will take about four weeks. Two excavators with grab buckets will perform the demolition while workers spray water to keep the dust down. The loudest part of the demolition will be in the second to third week, when the contractor breaks up the concrete foundation and hauls the debris offsite. When the demolition is complete, workers will remove a large underground fuel oil storage tank. The new Upper School will be entirely heated and cooled using geothermal energy.
September 24, 2024
As some of you may have noticed, Washington Gas is preparing to make improvements to its underground infrastructure at and around the intersection of Quebec Street and 37th Street. Washington Gas says the work will continue for 10-12 weeks. This is unrelated to our Upton Street project.
September 3, 2024
We have three post-Labor Day updates:
- Interior demolition on the first floor of the Upton building will wrap up by the end of the week.
- You may see some electrical work taking place this month. Today, September 3, PEPCO technicians will disconnect the building’s electrical transformer, which sits near the sidewalk on 37th Street. To maintain power, the contractor will install a temporary generator near the loading dock on the east side of the building, closer to the Sidwell Friends campus. That unit will run only during construction hours and will be screened to minimize noise. Then, later in September, PEPCO will install new—still temporary—service to a shed adjacent to the 37th Street entrance that will replace the generator as the primary power source.
- The contractor will meet with city inspectors in early September as a prelude to installation of fencing, wood chips, and a watering system to protect existing trees, including special and heritage trees. Later this month, workers will install erosion and siltation control measures around the property.
August 23, 2024
Wonder what’s happening inside the Upton building? Here’s a glimpse, captured this week by our digital producer. A LOT has changed since June!
August 12, 2024
We have received a list of projected start and end dates for some of the major work on the project that is most likely to create above-average noise levels on the worksite. As the start date for each of these activities approaches, we will provide more detailed information.
- Late August – October 2024: Demolition of a portion of the building on the east (37th Street) side
- October – December 2024: Installation of micro-piles that will support areas of new construction
- October 2024 – May 2025: Work on building façade, including areas of new construction
- December 2024 – March 2025: Installation of structural steel in areas of new construction
- July – November 2025: Installation of utilities on the project site.
- March – August 2025: Digging of geothermal wells
August 5, 2024
This morning a crane operator arrived on campus at 6:15 a.m., long before the agreed-upon start time of 10 a.m. The crane was on campus to do work at the Middle School unrelated to the Upton project. We apologize for the noise this caused and the contractor that hired the crane has apologized as well.
July 22, 2024
Progress continues on the interior of the building. Demolition underway and will be completed by the end of August. Removal of asbestos by a licensed abatement contractor is scheduled to end in mid-August. Here’s a list of other work that will taking place over the summer:
- Early August: Workers will begin digging plumbing pipe trenches in the existing 1st floor concrete slab floor; that work will continue through early September.
- Early August: Installation will begin of erosion and siltration control measures surrounding the site. This will consist of a black mesh-fabric fence and filter barriers at the stormwater drains along the road.
- Mid August: Tree-protection work will begin, consisting of special fencing, woodchips, and regular watering to project existing trees, including many special and heritage trees.
- Late August: Crews will removal of the existing underground fuel storage tank adjacent to the building and begin demolition of a section of the building on the eastern (37th Street) side.
June 17, 2024
Work to renovate the building began in June 2024 with the installation of a protective perimeter fence. The new Upper School will open in time for the start of the 2026-27 academic year.
Livestream Monitoring Video of Upton Street and 37th Street
By agreement with our neighbors, Sidwell Friends has positioned two video cameras near the corner of 37th Street and Upton Street. One camera faces south on 37th Street; the other faces west on Upton Street. These cameras provide real-time video of vehicles as vehicles entering and leaving the construction site along both streets. They will be in place until the project is complete.
37th Street View
Upton Street View
New Upper School at a Glance
The new Upper School will replace the existing 1964 structure and its 1997 addition. Some highlights:
- Geo-thermal wells and solar panels will generate renewable energy and put the School on a path to creating a carbon-neutral campus.
- The Learning Commons will create a new academic hub as home to the library, student technology support, quiet study areas, and the School Archives.
- Eleven science labs and three science courtyards will expand opportunities for research and create flexible space for robotics and science projects.
- “Quaker Commons” will provide open and flexible dining spaces indoors and out and will feature a teaching kitchen that can serve as a classroom and gathering space.
- The Fox Den store and coffee shop will serve as a gathering spot for all to meet and relax.
- The Center for Ethical Leadership will support community-service initiatives and provide resources to affinity groups across all grades at the School.
- The Center for Teaching and Learning will provide a space for faculty education and training, with a prototype classroom for testing new approaches and technologies.
Project Goals
Sidwell Friends School acquired Upton Street property and building from Washington Home & Community Hospices in 2017 after the non-profit organization decided to close and sell the nursing home and transition to an in-home hospice care model. For Sidwell, this presented an unexpected opportunity to add an adjacent six-acre property—one that would allow the School to reunite its three divisions—Lower, Middle, and Upper School—on to one campus.
The School spent the next seven years raising the more than $110 million needed to pay for the purchase and the cost of renovating the building.
Once complete, the New Upper School will become a vibrant and collaborative environment for students and faculty. Unifying the School will benefit every student by facilitating engagement between age groups and fostering an even stronger sense of community. Teachers will have more opportunities to partner across divisions and will have greater access to professional development tools through the new Center for Teaching and Learning.
In addition, managing one campus will increase operational efficiency, lower costs, and decrease the School’s environmental footprint.
Building Renderings
Drop-off Courtyard
Drop-off Courtyard
Third Floor Entrance
Third Floor Entrance
Science Center / Stairs to Learning Commons
Outdoor Dining
Main Dining
Community Dining Facility
Teaching Kitchen
Science Commons and Labs
Robotics Classroom
Robotics Test Space
Learning Commons
Fireplace Common Space
Open Area for Students to Gather
School Archives
Fox Den Cafe and Store
Fox Den Cafe and Store
Fox Den Cafe and Store
Center for Ethical Leadership Entrance & Gallery
Common Area Inside Center for Ethical Leadership
Presentation Space Inside Center for Ethical Leadership
Center for Teaching and Learning
Faculty Learning Space
Prototype Classroom